Existing pupil place capacity of school: 282
Pupil place capacity after addition: 409
Projected 2018 enrolment: 402
3 New Full Day Kindergarten (FDK) rooms
New Library
New Staff Room
New Vice Principal’s Office
New FDK playground
New fire route to the addition
existing staff room to new Special Education room
existing library to classroom
existing kindergarten rooms back to regular classroom use
and interior renovations which will include new second floor washrooms and installation of an elevator
$2,603,036.80 (including net HST)
$3,059,067 (including parking lot work completed last summer)
Anticipated completion of the School Addition is late fall to early winter 2104.
Interior renovations are to be completed this summer, with the exception of the elevator which may take longer.
Work inside the existing school will be carried out after school hours in the fall.
Portable to be removed from the site by 2018, based on current enrolment projection.