Page Content
St. Augustine New Construction
Addition
Update on New Funding for Addition to St. Augustine, November 19, 2015
St Augustine of Canterbury - Letter for parents, staff and caregivers
St Augustine - Phase 1 - Floor Plan
St Augustine - Phase 1 - Rendering
St Augustine - Phase 1 - Site Plan
New Construction Status Update
June 2020
March 2020
December 2019: Most deficiencies affecting school operations were completed by December 6, 2019, and outstanding commissioning will be completed once the colder temperatures are more consistent. Remaining door hardware, exterior fencing and gym padding to be completed by January 6, 2020, and pavement line painting will be completed in Spring 2020.
- September 2019: The majority of the outstanding work is in the front yard, and includes the childcare playground and front yard sodding. Work is scheduled to be complete the first week of October, and the childcare anticipates opening its three full time rooms in December 2019 or January 2020.
ba0d1930-527f-47e4-b4b3-aeecd110160e|7ec65526-f8ab-403c-92d7-a12532461828;de4a63f9-f9f3-43a3-a18a-be24d119bd7f|c95b8457-822b-43bb-a2a3-50ef7888ff1b;
03256bc0-7684-4ed8-a21d-edfc8b19d22b