Here are the latest updates and information regarding the new construction at St Augustine Catholic School
December 2019: Most deficiencies affecting school operations were completed by December 6, 2019, and outstanding commissioning will be completed once the colder temperatures are more consistent. Remaining door hardware, exterior fencing and gym padding to be completed by January 6, 2020, and pavement line painting will be completed in Spring 2020.
September 2019: The majority of the outstanding work is in the front yard, and includes the childcare playground and front yard sodding. Work is scheduled to be complete the first week of October, and the childcare anticipates opening its three full time rooms in December 2019 or January 2020.
June-Sept 2016 Status Update
May 2016 Status Update
November 2014 Status Update (1)